What inspections are required?
Most projects require four inspections, though this can vary. Speak with a Building Inspector to confirm what your specific project needs. It’s your responsibility to notify the inspector when you’re ready for each inspection.
Inspection stages:
Preliminary Inspection (48 hours before starting work):
•Excavation depth
•Removal of organic materials
•Soil type/compaction
•Setbacks
Pre-Backfill Inspection (48 hours before backfilling foundation):
•Drain tile and cover placement
•Damproofing (e.g., tar)
•Foundation depth
•Concrete quality
•Backfill materials
•Footing/wall sizes
•Anchor bolts
Structural Inspection (72 hours before interior wall finish):
•Structural elements (beams, trusses, framing, etc.)
•Insulation, vapour/air barrier
•Ventilation
•Stair framing
•Bedroom window sizes
•Backfill height (exterior)
•Roofing and siding
Final Inspection (10 days before completion):
•Railings and guards
•Smoke alarms
•Garage door hinges (self-closing)
•Exterior decks and stairs
•Ventilation systems